Production Jobs / RS-1042

Dana & Mike Whitfield

On TrackArchitectural ReplacementProperty dossier →View as homeowner →
4127 Briar Ridge Ln, Dublin, OH 43017(614) 555-0182dwhitfield@gmail.com
Revised contract
$26,551
Original $24,850 + approved changes $1,701
  1. Sold Job
  2. Pre-Production
  3. Materials
  4. Crew & Schedule
  5. 5
    Installation
  6. 6
    Completion
  7. 7
    Financial Close
Next: Complete field check-ins
Owner: Carlos Rivera · Due: Nov 5, 2026 · Blocker: None
Released to build
Revised Contract
$26,551
Original $24,850 · approved changes only
Actual Incurred Cost
$20,110
Estimated $18,300
Forecast Gross Profit
$6,441
Est. $6,550
Forecast Final Margin
24.3%
▼ 2.1 pts vs. 26.4% est.
Estimated Budget
$18,300
Committed Cost
$20,110
Issued POs and crew agreements only
Remaining Forecast Cost
$0
Forecast Final Cost
$20,110

Estimated vs Actual by Category

Variance Detail

CategoryEst.ActualVar.
Materials$9,850$10,120+$270
Labor$6,200$6,480+$280
Subcontractors$1,400$1,400$0
Dumpsters / Equipment$850$850$0
Change-Related Costs$0$1,260+$1,260

Field Labor Capture

Posted to actuals
Rivera Crew A · piece rate × 32.4 measured squares
Posting moves $2,203 into Labor actuals and locks the crew commitment — forecast margin updates instantly.

Committed vs. Invoiced

Committed = POs issued & subcontracts signed · Invoiced = bills received
MaterialsInvoiced $10,120 of committed $10,120
LaborInvoiced $6,480 of committed $6,480
SubcontractorsInvoiced $1,400 of committed $1,400
Dumpsters / EquipmentInvoiced $850 of committed $850
Change-Related CostsInvoiced $1,260 of committed $1,260
Invoiced Committed
Total exposure: $20,110 committed · $20,110 invoiced to date