Production Jobs / RS-1027

Grace Liu

CompleteStorm RepairProperty dossier →View as homeowner →
1904 Sawmill Pkwy, Powell, OH 43065(614) 555-0166gliu@proton.me
Revised contract
$14,632
Original $14,200 + approved changes $432
  1. Sold Job
  2. Pre-Production
  3. Materials
  4. Crew & Schedule
  5. Installation
  6. Completion
  7. 7
    Financial Close
Next: Review warranty and closeout
Owner: Carlos Rivera · Due: Oct 3, 2026 · Blocker: None
Closed
Revised Contract
$14,632
Original $14,200 · approved changes only
Actual Incurred Cost
$10,050
Estimated $9,900
Forecast Gross Profit
$4,582
Est. $4,300
Forecast Final Margin
31.3%
▲ 1.0 pts vs. 30.3% est.
Estimated Budget
$9,900
Committed Cost
$10,220
Issued POs and crew agreements only
Remaining Forecast Cost
$0
Forecast Final Cost
$10,050

Estimated vs Actual by Category

Variance Detail

CategoryEst.ActualVar.
Materials$5,600$5,480-$120
Labor$3,700$3,650-$50
Subcontractors$0—pending
Dumpsters / Equipment$600$600$0
Change-Related Costs$0$320+$320

Field Labor Capture

Posted to actuals
Rivera Crew A · piece rate × 19.5 measured squares
Posting moves $1,326 into Labor actuals and locks the crew commitment — forecast margin updates instantly.

Committed vs. Invoiced

Committed = POs issued & subcontracts signed · Invoiced = bills received
MaterialsInvoiced $5,480 of committed $5,600 · $120 open
LaborInvoiced $3,650 of committed $3,700 · $50 open
SubcontractorsInvoiced — of committed $0
Dumpsters / EquipmentInvoiced $600 of committed $600
Change-Related CostsInvoiced $320 of committed $320
Invoiced Committed
Total exposure: $10,220 committed · $10,050 invoiced to date